Esk & Lowood 5ML Balance Tanks

PROJECT DESCRIPTION

Design and Construct of two 5 ML Reservoirs at Esk and Lowood using post-tensioned floor and precast post-tensioned walls panels and associated pipeworks

PROJECT DETAILS

Client Western Pipeline Alliance
Superintendent Abigroup/McConnell Dowell Joint Venture
Project location Esk, Queensland | Lowood, Queensland
Contract system Design & Construct
Reservoir capacity 2x 5ML
Contract sum $3.4 Million
Completion date April 2008