Landers WTP: Fluoride and Service Water Upgrade
Scope includes upgrading the plants service water and fluoride capacity which included the following:
Piling for New Service Water Building
Foundation preparation
Construct new block building
Installation of new multistage water pumps
Decommission and Removal of the existing fluoride equipment
Modify existing fluoride building
Installation of new Fluoride equipment
Installation of new service water and sludge pipework
Electrical and mechanical works
Roadworks
Testing and commissioning

PROJECT DETAILS

Client SEQ Water
Project Location Landers Shute Qld
Contract System Design and Construct
Contract Sum $7.15 Million
Completion Date December 2024